Google


The web Upton website

 

 

 

Riverside Flood Defences

Layout Drawing
Thanks to Peter Booth for aligning the drawing properly

2012

W/C 19th February

The fencing was removed from alongside the Swan. Piling continues opposite the Kings Head. Underground CCTV vans and a drainage tanker were busy by the Kings Head. The large wall by Bankside House has been bricked over. The flood wall in Dunns Lane is being topped off with a flat layer of bricks. The road between the Plough & Kings Head is being cleared of old concrete.

General pictures of progress

 

W/C 12th February

On Tuesday the road along by the Swan was fenced off. Access to the houses has been left free. The area from Bridge House to Severn Leisure is being tidied after piling in preparation for digging out the earth ready for the wall foundations. On Wednesday huge lengths of timber were laid along the top of the built-up area in the river in preparation for the railings by the Swan being removed. Piling from Severn Leisure to the Kings Head continues.

General pictures of progress

 

W/C 5th February

Not much happened on Monday. On Tuesday, some brickwork and work on the rockery. By Thursday it appeared that the work in the river had finished. Work mostly at a standstill due to the very cold weather.

General pictures of progress

 
W/C 29th January

The 'rockery' is growing. Two digging machines are working now, one on the pile of stones and one on the land. Parts of the other side of one of the old bridges have now been uncovered. From Tuesday, work on piling and bricklaying was delayed due to the very cold weather. By Thursday the area between the Kings Head and in front of Bridge House had been prepared for piling. Large bags of small rock were being placed on the 'rockery', building up the area.

General pictures of progress

Environment Agency video of the Heritage Day about the old bridges

 

W/C 22nd January

Piling couldn't start outside Severn Leisure on Monday, as the machine was busy elsewhere. The stone platform is growing. On Tuesday, piling commenced. Excavation work on the old bridges continues, with several of the stones having been removed. On Wednesday the old bridge area was being covered and prepared for work on the wall. Thursday & Friday, bricks were laid opposite the Plough, where the wall joins the bridge, and in Dunns Lane.

General pictures of progress

 

W/C 15th January

Work commenced building up the bank alongside the Swan. Loads of large stones are being delivered by lorry from a quarry near Leicester and dropped into the river. On Wednesday bricklaying recommenced, having stopped because of heavy frosts. The remains of old bridges are being uncovered and prepared for the archaeology day on Friday.

Videos of the work to build up the banks

Press release

General pictures of progress

EA January update

 

W/C 8th January

Brickwork started. The lower bricks are engineering bricks and won't be visible when the wall is finished. On 10th January work commenced laying the facing bricks. The shuttering for the new wall by Bankside House appears to be in place. The electricity cables that went over the river from Lower High Street have been removed. The supply for East Waterside is now taken from that side of the river.

General pictures of progress

 

W/C 1st January

A quiet week. The core of the wall between the Plough & Kings Head has been finished.

General pictures of progress

 

2011

W/C 18th December

General pictures of progress

 

W/C 11th December

Work commenced between the Disabled Area and Dunns Lane. Street furniture & turf removed and the working surface laid. More of the concrete core poured between the Plough & Kings Head.

General pictures of progress

EA December newsletter

 

W/C 4th December

Some engineering bricks (not facing) have arrived. Shuttering for the wall is still being erected. Infill between the foundations & the road continues. The first section of wall core has been poured.

General pictures of progress

 

November 2011

W/C 27th November

Work continues at both ends of the wall. The line of the wall can be seen from the reinforcement bars between the Plough & Kings Head.

General pictures of progress

 

W/C 20th November

The pouring of the concrete wall foundations started on Tuesday.

General pictures of progress

 

W/C 13th November

Piles have been drilled in Dunns Lane & preparation work for the gate commenced. Preparations for a second pouring of concrete along the riverfront between the Kings Head and the bridge are in progress.

General pictures of progress

 

W/C 6th November

Work has recommenced on the green in Dunns Lane. Concrete is being laid at the other end of the project.

General pictures of progress

 

September / October 2011

 

W/C 30th October

Work by the bridge was halted because some skeletons from the old cemetery were found. Digging around the piles continued. Work on the green in Dunns Lane halted. Apparently the river bank is collapsing. Cracks were observed during the summer.

General pictures of progress

 

W/C 23rd October

Piling continued up to the Kings Head River Terrace. Work started in Dunns Lane. Work started around the first piles by the bridge.

General pictures of progress

 

W/C 16th October

Work continued on putting in the piles

General pictures of progress

 

W/C 9th October

The road prepared for the piling machine. Piling started.

General pictures of progress

 

W/C 2nd October

Lamp posts removed. Preparations for piling machine. Lime trees pollarded.

General pictures of progress

 

W/C 25th September

Work continues on removing the paviers. The fencing around the Kings Head River Terrace has been removed. Netting to protect pedestrians from flying debris has been put on the security fencing. The footpath along the riverside is no longer accessible and notices saying 'No Mooring' have gone up. The paviers are being stacked on pallets and wrapped in preparation for storage. They will be replaced when the wall is built. Historic stones removed.

General pictures of progress

 

W/C 18th September

Morrison Construction took possession of the area from the bridge to the Kings Head on the 19th. Security fencing was put in place along the road, leaving the pavement free for pedestrians. On Tuesday the street furniture - seats and bollards - were removed. Upton in Bloom's floral tubs were transported to the footpath on Hanley Road. Gas services are being moved. On Wednesday & Thursday the large kerbstones and some of the road surface were removed.

General pictures of progress