October 2004 Work on the piles was completed on 22nd October. Most of the large cranes were removed during the week. The piles are now being topped with a steel cage over which concrete is being poured to form the base for the cross members of the new viaduct. Conditions are worsening with daily rain causing the ground to be |
|