September 22-27: following the problems with the first pile, progress has picked up. The third picture shows a broken drill which was recovered from the bottom of pile two. The water filtration tanks can be seen along with the outflow of clean water into the culvert. Following these, a sequence of pictures showing the filling of pile 2 with concrete. The last picture shows piles 1 and 2 filled, piles 4 and 6 drilled. On 28th September pile 6 was filled with concrete. |
|