Another award - October 2005
Opening ceremony leaflet
July 17th - the Opening Ceremony
July 7th 2005
July 5th 2005
The viaduct wins awards
June - restoration continues
May - finishing off and restoration
April
Leaflet Issue No 4 April 2005
March 5th -31st
March 9th - new sign!
16th February - March 3rd
February 15th
January 31st
January 20th including site visit
First concrete pour finished
January 7th
16th December - 6th January
1st to 13th December
23rd to 30th November
21st & 22nd November
11th & 12th November
November 9th - the first cross piece beams
October 23rd to November 3rd
October 20th to 22nd
October 2004, to the 15th
Leaflet Issue 3, September 2004
September 2004
Pictures of the internal damage
August 2004
31st July - the temporary road is open
30th July
29th July
28th July
27th July
26th July - tarmac & lamp posts
12 - 23 July
2nd week July
Temporary road underway, 1st Week July
Leaflet issued at a meeting held on 2nd July 2004
Pictures taken in June
2nd July Meeting notice
Letter in the Malvern Gazette, 11th June
Letter in the Malvern Gazette, 4th June
24th May, new concrete width restrictions
23rd May, car stuck!
Worcester Evening News 19th May
Thoughtless motorist(s)
Viaduct report - Worcester Evening News 14th May
Upton Viaduct pictorial record 30/4/4-11/5/4
Upton Viaduct Leaflet (2 large pictures approximately 300K total)
|
Worcestershire Highways Partnership Unit in Malvern
News in PDF documents
A4104 Upton Flood Viaduct restrictions, Worcestershire CC information
The Worcester Evening News
The Malvern Gazette |